Timeline

2007
December 14

December 2007: Regulating and Metering (R&M) Station in Takoradi ready to receive uncompressed natural gas

November 14

Offshore pipeline ready for commissioning

November 2007:  Offshore pipeline ready for commissioning
September 14

Onshore civil construction in Benin begins

September 2007:  Onshore civil construction in Benin begins
August 14

Onshore civil construction in Togo starts

August 2007:  Onshore civil construction in Togo starts
April 14

Completion of the first of Year One Community Development Project in Benin

April 2007: Completion of the first of Year One Community Development Project in Benin
March 14

First batch of completed Community Development Projects in  Ghana and Nigeria Commissioned

March 2007:  First batch of completed Community Development Projects in Ghana and Nigeria Commissioned
2006
August 14

Construction of WAPCo’s Community Development Projects begins

August 2006:  Construction of WAPCo’s Community Development Projects begins
April 14

Construction of compressor station in Nigeria commences   

April 2006: Construction of compressor station in Nigeria commences
March 14

Onshore civil construction begins in Nigeria and Ghana

March 2006: Onshore civil construction begins in Nigeria and Ghana
2005
August 14

Offshore construction of West African Gas Pipeline commences

August 2005:  Offshore construction of West African Gas Pipeline commences
.