History
Timeline
2011
January 2011: First natural gas delivered through WAGP to Togo
2010
Lagos Beach Compressor Station completed
December 2010: Lagos Beach Compressor Station completed
Lagos Beach Compressor Station completed
December 2010: Lagos Beach Compressor Station completed
December 2010: WAPCo Starts full commissioning of WAGP system.
Volta River Authority receives gas at Tema R&M for the first time
August 2010: Volta River Authority receives gas at Tema R&M for the first time
August 2010: Volta River Authority receives gas at Tema R&M for the first time
August 2010: Volta River Authority receives gas at Tema R&M for the first time
2009
Ghana’s Volta River Authority generates electricity with natural gas from WAGP
April 2009: Ghana’s Volta River Authority generates electricity with natural gas from WAGP
2008
December 2008: First natural gas supply through WAGP arrives in Ghana
December 2008: First natural gas supply through WAGP arrives in Ghana
Hand over of the first of Year One CDP in Togo
October 2008: Hand over of the first of Year One CDP in Togo
Commissioning of onshore and offshore pipeline begins with the opening of valves at Itoki inlet
April 2008: Commissioning of onshore and offshore pipeline begins with the opening of valves at Itoki inlet