Our Journey Through the Years

History


Timeline

2018
February 1

Site construction work begins at Takoradi Regulating & Metering station, under the Takoradi to Tema Interconnection Project (TTIP)

February 2018:  Site construction work begins at Takoradi Regulating & Metering station, of the Tema-Takoradi inter-connection project
2017
December 18

Tema expansion from 70mmscfd capacity to 140mmscfd capacity completed

December 18, 2017:   Completion of the Tema expansion from 70mmscfd capacity to 140mmscfd capacity
June 1

Axxela Limited is registered as shipper on WAGP   

June 1, 2017:  Axxela Limited is registered as shipper on WAGP
January 1

Project engineering begins on Takoradi to Tema Interconnection to enable reverse flow of natural gas from the Western fields in Ghana

January 2017:  Project engineering begins on Takoradi to Tema Interconnection to enable reverse flow of natural gas from the Western fields in Ghana
2016
April 1

Ghana National Gas is registered as shipper on WAGP

April 1, 2016:  Ghana National Gas is registered as shipper on WAGP
2015
December 1

Gasol Plc is registered as a shipper on WAGP

December 1, 2015: Gasol Plc is registered as a shipper on WAGP
January 1

Nigerian Gas Company (NGC) Ltd. is registered as shipper on WAGP

January 1, 2015:  Nigerian Gas Company (NGC) Ltd. is registered as a shipper on WAGP
2012
July 1

Pipeline now open to all shippers

July 1, 2012:  Pipeline now open to all shippers
2011
March 14

Commercial Operations Dated declared

March 2011:  Commercial Operations Dated declared
February 14

Compressed gas transported on WAGP for the first time

February 2011: Compressed gas transported on WAGP for the first time
.